The next huge hurdle was to understand exactly where + POOL could go. Before we could go to the City of New York to start talking about where they might let us build + POOL, we had to figure out exactly where it would physically fit. This included not only testing water quality to determine how + POOL’s filtration system might affect different sites, but also studying each site’s physical conditions: available surface area, water depth, current speeds, 100 yr flood wave height, tide elevation differences, general harbor conditions.
The process took nearly 6 months, studying upwards of 12 sites all over New York City, working closely with our marine engineers at McLaren Engineering.